AM increases SSC capacity by 100,000 mt in Neuwied

ArcelorMittal is increasing the capacity of its sheet service centre in Neuwied, northwestern Germany, by 100,000 mt to 500,000 mt/year, the company said Tuesday.

The company is investing €16.50 million in the SSC, which processes sheet from its own Bremen, Eisenhuettenstadt and Ghent mills. The investment also comprises of a new slitting line, crane facility and a cutter block.

The slitting line is expected to be operational by the end of this year and increase the annual capacity of the site by 100,000 mt. The line can slit coils with a thickness of up to 4mm.

“We are investing in a significant capacity expansion and several automation projects to increase productivity and health and safety at the sote, said managing director Friedrich Raffauf. Neuwied supplies primarily the automotive, mechanical engineering and plant manufacturing industry, the company said.

The SSC, which has its own jetty to the river Rhine, was opened in 1998. ArcelorMittal has six service centers in Germany and 16 distribution centers, as well as its integrated flats and longs works.

Laura Varriale, PLATTS

ArcelorMittal makes major investment in German service centre

ArcelorMittal is investing a total of €16.5 million ($20.1m) in its steel service centre in Neuwied on the Rhine, Kallanish learns from the company.

It has already spent €6.5m, and will spend another €10m up to the end of the year, some of which will be invested in setting up a new slitting line.

In January, the Neuwied site began operating a new slitter shaft robot, with a second one following in March. The robots will automatically equip the steel shafts with blades weighing 20 kg, and then forward the shafts into the coil cutting machinery. The automation of this process increases operator safety the company says. Two new crane units will also be ready to start operation in March

The new slitting line intended to commence operations at the end of the year will be able to handle coils of 30 tonnes weight and a strip thickness of up to 4mm. Neuwied will then be able to raise its production capacity by another 100,000 tonnes/year, in addition to its current capacity of 400,000 tonnes. The new line will also be equipped with slitter shaft robots and automatic separation shafts. In addition, there will be a new packaging line that automatically prepares cut sheet and coil for transport.

Managing director Friedrich Raffauf says that the modernisation will mean that employees are spared from the dangerous handling of heavy machinery. The Neuwied plant employs 100 people and processes strip from the group’s mills in Ghent, Bremen and Eisenhüttenstadt.