AM Italia negotiating operating rights with government

ArcelorMittal is negotiating with the Italian government for a solution to allow the continued operation of its ArcelorMittal Italia subsidiary from September 7, when a current legal safeguard for its operation expires, Lakshmi Mittal, ArcelorMittal chairman and CEO, said Thursday.

“Our expectation is that measures will be in place by September 6,” Mittal told investors on a webcast to discuss the company’s second quarter results. “We are in negotiation with the Italian government, which is working on providing us with legal safeguards…the works should continue to operate [however] no assurance can be given at this point in time.”

The AM Italia — known as Ilva before ArcelorMittal took it over last year — has not been environmentally compliant for some time. It has been given license to operate under government protection until September 6. However, the situation regarding any future license to operate the works is still unclear following a recent fatal accident on raw materials Pier No. 4 at the works in Taranto.

The latest accident occurred on the heels of an Italian public prosecutor ordering a production halt of blast furnace No. 2, following allegations that improvements promised for the works after an accident there in 2015 — when the mill was under previous management — had not been fully undertaken.

Mittal confirmed Thursday that Pier No. 4 continues under seizure. With operations currently only at Pier No. 2, the works is losing inputs of 10,000 mt/day of raw materials, which means the steelworks is currently producing at between 3 million mt and 3.5 million mt/year capacity, he said. “We don’t expect the situation to last indefinitely,” he said. All blast furnaces at the works are currently in operation, he said.

“ArcelorMittal aims to dramatically improve the performance of ArcelorMittal Italia in the second half,” Mittal said.

But the plant’s expected ramp-up to a 6 million mt/year run-rate, previously expected by H2 2019, has been slowed due to weak market conditions, ArcelorMittal said in its investor presentation. 

ArcelorMittal has a net capex commitment at ArcelorMittal Italia of Eur2.10 billion ($2.33 billion) through 2024, around half of which is in environmental measures, with all interventions in this area progressing in line with an accelerated timetable, according to the presentation.

— Diana Kinch

AM urges tighter controls, carbon taxes on EU steel imports

The European Commission’s steel import safeguards scheme must be strengthened to achieve the end it was designed for in a “highly challenging market,” ArcelorMittal CEO Lakshmi Mittal said Thursday.

In addition, all steel used in the EU needs to be subject to the same carbon levies as products made within the EU, Mittal said during a webcast with investors.

“We need an improvement in the safeguards,” said Mittal, noting that the EC’s current review of the safeguards will end on September 30. ArcelorMittal has opted to reduce its flat steel production capacity by 4.2 million mt/year in Europe in a move to better balance supplies and demand. The company will also destock in Europe in the second half which may be positive for prices, he said.

“It’s very hard for anyone to have a decent return, therefore production has to go down to give better results,” Mittal said.

Luxembourg-based ArcelorMittal swung to a net loss of $447 million for the three months ended June 30, against a net profit of $1.87 billion year on year, the global steelmaker said Thursday, amid weak demand and high import levels in Europe and extraordinary charges on operations in Italy and the US.

According to European Steel Association Eurofer, steel imports into the EU still accounted for nearly one quarter of regional consumption in Q1 despite the introduction of the quotas system on imports last year. Steel markets were buoyant for most of 2018 but at the end of that year started to suffer a “surprising downturn” followed by soaring key steelmaking raw materials prices, Mittal said. Steel consumption in China however continues “fundamentally in positive territory,” he added.

ArcelorMittal has no plans to take down capacity in the US and is proceeding with a hot-rolled coil expansion in Mexico and a cold-rolled, coated and galvanized steel expansion in Brazil, Mittal said. A positive performance in its mining division, which has benefited from high iron ore prices, “highlights the benefits of diversification,” he said.

Still, asset divestments will occur over the next two years, as the company embarks on a portfolio optimization program worth $2 billion, in a move to reduce net debt.

“Now we need to identify the assets,” Mittal said.

In Europe, Mittal indicated he was encouraged by a recent statement by Ursula van der Leyden, the incoming president of the EU Commission, of a “green border adjustment” which would mean steel products entering the EU would be subject to similar carbon costs as steel produced within the region. Carbon emissions costs under the Emissions Trading Scheme to which EU steelmakers are tied are currently at an 11-year high.

ArcelorMittal is developing three pathways to reduce carbon emissions from steelmaking, including hydrogen-based ironmaking, use of circular carbon energy sources and carbon capture and storage.

“All solutions we developed are unique and ahead of the curve,” Mittal said. “But to develop all these we need a level playing field.”

— Diana Kinch

ArcelorMittal Italia to shut down Taranto furnace

Italian authorities have rejected a request by the extraordinary commissioners of the former Ilva company to carry out remedial work on blast furnace No. 2 at the Taranto mill now run by ArcelorMittal Italia. The furnace will now be shut down, the steelmaker says in a note monitored by Kallanish.

ArcelorMittal Italia is investigating the repercussions that the decision may have for the Taranto plant. It hopes that an alternative solution may be found to the closure as BF 2 is an integral part of the Taranto site it says, although the steelmaker is not party to the legal procedure.

The order by the authorities to shut down the furnace was passed in early July (see Kallanish 10 July).

ArcelorMittal now finds itself in a difficult situation with its Italian acquisition. The new Italian government is trying to make the company take responsibility for costs arising from environmental issues which arose before the site was acquired from Ilva. Previous reports have suggested that, under the terms of the acquisition, the ArcelorMittal group may be able to relinquish control of the mill in early September, should a solution not be found.

Klöckner foresees no major partnership with tk Materials

The often-rumoured potential of  Klöckner going for a major joint venture with thyssenkrupp’s distribution unit Material Services is largely off the table, says Klöckner’s ceo, Gisbert Rühl.

A press report last week of a meeting of the top management of both companies had refuelled such speculation. However, Rühl played down its significance in his company’s results conference call this week. “Of course, we are talking to (thyssenkrupp ceo) Guido Kerkhoff. We do meet sometimes, we even live in the same neighbourhood in Essen, after all,” he told Kallanish.

Consideration of taking a major stake in tk Materials Services essentially expired when tk AG re-declared steel as one of its core businesses after the failure to merge tk Steel with Tata, Rühl said. There was never any active ambition from Klöckner’s side in that direction, and any deal would have been a result of the earlier circumstances if tk had integrated with Tata, he stressed.

Klöckner still remains open to some form of cooperation, “… and we can imagine taking a minority stake, for example, but essentially we are not looking for acquisitions these days,” Rühl said. He noted that the company is currently busy with restructuring its operating business, delegating responsibilities down to the country units, that have previously been held by the holding company.