Steelmaker SSAB finalises temporary layoffs in Europe

Nordic steel producer SSAB will implement temporary staff layoffs lasting two-three weeks over the rest of this year.

The SSAB Europe division, which has its largest sites at Raahe and Hameenlinna in Finland, employs almost 4,000 workers. Employees will not be paid during the layoffs. How the cuts will be allocated will be determined in the coming weeks, the company said.

SSAB will continue to apply the flexible “working-time bank” with production workers at its Sweden operations, and is in dialogue with trade union IF Metall regarding the measures. The working-time bank can be used when there are longer maintenance periods, or to accommodate periods of lower production.

SSAB is also planning flexible working arrangements with office staff in Sweden, which will be implemented during the fourth quarter.

As with other European mills, SSAB is battling with weaker steel demand and prices, increased competition from imports and higher costs.

Argus‘ headline northwest Europe hot-rolled coil index slipped from €535/t ex-works on 12 November 2018 to €457.75/t today. At the same time, iron ore has risen to $96.60/dmt from $76.25/dmt, resulting in a substantial margin squeeze for mills.

ArcelorMittal Poland finalises blast furnace revamp agreement

ArcelorMittal Poland (AMP) has finalised with Mostostal Zabrze the PLN 27 million ($7m) agreement to revamp blast furnace no.3 at its flagship Dabrowa Gornicza plant, Kallanish learns from the Polish construction company. Work is scheduled for completion by mid-2020.

The two firms signed in August a letter of intent for the revamp (see Kallanish passim).

AMP postponed its plan announced in May to idle the remaining operational Krakow blast furnace on account of reduced demand, and increased costs and imports. ArcelorMittal’s sales in Poland slumped -12% on-year in the first half of 2019 to $2.11 billion. Since ArcelorMittal’s sale to Liberty of its Ostrava and Galati mills, AMP has become the focal point of the steelmaker in Central and Eastern Europe.

Schmolz+Bickenbach cuts back production

Due to lower demand from the automotive industry in particular, Schmolz+Bickenbach (S+B) is reducing production at its plants in Switzerland and Germany.

In September, short working hours have been introduced at both its speciality bar-making subsidiaries Swiss Steel and Deutsche Edelstahlwerke (DEW), S+B tells Kallanish upon request. Swiss Steel will have two weeks of reduced working in September, following a similar two weeks in May. At DEW, short working hours will apply as from calendar week 38. For the German operations, the company did not specify the duration.

“If and for how long short hours will prevail afterwards depends on the future development of demand. For the other business units, reduced working hours are not envisaged,” S+B says in a statement.

At the end of the second quarter, the order backlog of the group stood at 480,000 tonnes, after having had 571,000t at the end of Q1, and 612,000t at the end of 2018. “We do expect a gradual recovery in order intake at the end of this year, given that the depletion of inventories in the automotive value chain has made progress,” S+B states.

A Swiss newspaper report notes that the company has reduced its intake of production materials, highlighting the purchase of graphite electrodes used at the EAF furnaces. Last week, S+B lowered its guidance for this year’s Ebit for the full year for the second time to a further revised figure of €70-100 million ($77-110m).