ArcelorMittal moves on with Florange galv line construction

The new galvanizing line at ArcelorMittal’s mill in Florange in north-eastern France is currently under construction, Kallanish learns from the company.
With start-up expected by the end of the year, the new line will eventually produce 800,000 tonnes of high-strength automotive steel over time and will ultimately employ 80 people, including 25 new hires.
“For this project, the region will provide support for the acquisition of equipment. The aim is to strengthen the future of the Florange site as a specialist in high value-added automotive steel,” ArcelorMittal reveals in a note. This is part of a major investment in the group’s automotive steel production in France. The company will spend a total of €96 million ($107.5m) on improving its facilities in Florange and Dunkerque (see Kallanish 30 July 2017).
Last year Florange set a new site record for galvanized steel production. Galvanizing line No. 1 at the site attained an output of 500,000t of galvaized product in 2018, a record for the line.
The ArcelorMittal site in Florange employs 2,300 people and produces 7 million tonnes/year of steel mainly for the automotive and packaging sectors, Kallanish notes.
Taranto troubles continue for ArcelorMittal Italia

ArcelorMittal’s problems at the former Ilva plant in Taranto have continued this week. On Tuesday the unions and the management met with the Italian economic development minister Luigi Di Maio to discuss the possibility that ArcelorMittal would cease control of the plant in early September. Meanwhile a local court judgement has confirmed that the company should prepare to idle blast furnace number 2 at the site.
Reports in Italian media this week confirmed that the contract signed between ArcelorMittal and the Italian authorities allows ArcelorMittal to rescind the agreement in case rules are changed after the contract is signed. The company would therefore appear to be able to relinquish control of the mill as soon as 6 September, Kallanishnotes. This is when the current decree could remove the existing legal safeguards in place to protect the group from incurring liability for environmental issues that occurred before it took control of the plant.
Di Maio explained during a meeting with the unions and the representatives of ArcelorMittal on Tuesday that legal immunity will not be given back to ArcelorMittal, despite the threats of closure. He assured that ArcelorMittal would not have problems as long as it respects the environmental plan, but this might not be sufficient.
Meanwhile, also on Tuesday, a local magistrate ordered ArcelorMittal to begin procedures to temporarily idle blast furnace number 2 of theTaranto plant. The request is linked to the conclusion of an investigation following a fatal accident which occurred in 2015.
ArcelorMittal could well come to an agreement with the magistrate over new remedies to ensure the safety of blast furnace number 2 and keep it open. This new issue at the mill however could well also impact the steelmaker’s upcoming decisions about running the former Ilva operations.
EUROMETAL management participated in a compliance training course

Fernando Espada, President of EUROMETAL, Daniel Guinabert, Director General of EUROMETAL and Ricardo Silva, EUROMETAL officer, attended a compliance training course in the offices of Henseler & Partner Rechtsanwälte mbB at Düsseldorf on 9 July 2019.
The aim of the course was refreshing and deepening knowledges on the topic of compliance within EUROMETAL as a trade association.
The content of the training:
- general introduction to the topic of compliance
- rights, duties and liability of management bodies / executive committees
- delegation of compliance duties / role of the Compliance Officer
- implications of anti-trust law
- current regulatory activities of competition authorities
- guidelines for association meetings
- components of a comprehensive compliance system
- corruption risks
A Compliance Training Certificate was delivered to all participants.