US enhances steel trade monitoring system

The US Department of Commerce on Friday released an enhanced version of its Global Steel Trade Monitor in an effort to provide users with the ability to better track global markets.

The improvements rolled out Friday include the ability for users to create graphs and charts to compare changes in trade patterns between two steel trading countries or two groups of steel products at one time, a function not previously available.

As with the original monitor, this enhanced version can generate more than 20,000 detailed charts for five standard aggregate steel mill product categories: flat, long, pipe and tube, semi-finished, and stainless products across the top 20 global steel importing and exporting countries, Commerce said.

The original interactive monitor was launched in September 2018.

— Justine Coyne

Italian flat products’ output falls again

Italian flat products’ output fell year-on-year in July, according to data released by local steelmakers’ association Federacciai, monitored by Kallanish. 

In July, flats output decreased year-on-year by -9.4% to 892,000 tonnes. Over the first seven months of the year output ticked up by 1.1% compared to the same period in 2018 however, reaching 6.8 million tonnes.

Italian longs output also increased in July, by 1.6% y-o-y to 1.6mt. It moved in the opposite direction over January-July, falling by -0.2% to 7.6mt.

In 2018 flats’ output fell by -2% on-year to 11.1mt. In full-year 2017 production of flats had dipped by -2.1% to 11.33mt, Federacciai confirms. Longs production in 2018, however, grew by 4.1% to 12.4mt, after it had grown by 2.3% y-o-y in 2017 to 11.9mt.

Sunningwell agrees to lease Huta Czestochowa

Sunningwell International Polska has signed an agreement to lease ISD Huta Czestochowa (HCz) for 12 months. The investment fund will pay a PLN 1.8 million ($453,000) leasing fee.

Sunningwell has already paid a deposit of PLN 6m and three months of rent. Its next rent payment for the following three months must be paid by 2 October. The firm also agreed it will be unable to lay off any workers or make capital expenditure on the plant without the permission of the administrator. Workers should be paid their outstanding wages by end-September.

Production must be restarted in October, failing which the administrator has the right to terminate the contract, the Czestochowa district court spokesman tells Kallanish.

HCz’s staff are due to return to work in the coming days to prepare for the production restart. The mill has to procure scrap and slab, while its equipment must be inspected. According to a note on HCz’s website, production at the meltshop will be restarted on 10 October, followed a few days later by the heavy plate mill. Sunningwell representatives plan to visit the steelworks on 23 September.

HCz initiated bankruptcy proceedings at the end of June after suspending production indefinitely in May due to a shortage in working capital needed to purchase scrap and pig iron feedstock (see Kallanish passim).

Electric arc furnace-based HCz has an 800,000 tonnes/year slab capacity and 1.2 million t/y capacity of heavy plate.

Liberty commits to $220 million Galati investment

Liberty Steel has committed to investing over €200 million ($220m) in its Galati steelworks to boost competitiveness, extend product range and support sales growth.

A sign of that investment in the former ArcelorMittal mill, which Liberty acquired in July, is the new cutting line commissioned last week, Liberty says. Following its acquisition of various ArcelorMittal plants in Europe, the UK-based firm now has a rolling capacity in excess of 18 million tonnes/year (see Kallanish 18 September).

Liberty Galati has a 3m t/y crude steel production capacity, selling to the construction, marine, oil, gas and wind energy sectors. This year production is foreseen at 2.1mt versus 1.7mt in 2018. The planned investment will take production over 3m t/y. Additional funds have also been set aside to fund significant strategic investments which are under development.

“We are committed to a programme of long-term investment in Romania, from making the Galati plant a beacon of strength and prosperity in the region to specific projects across our core sectors of aluminium, copper, energy and banking,” Sanjeev Gupta, executive chairman of Liberty parent company GFG, says in a note sent to Kallanish. “We look forward to working closely with the Prime Minister’s taskforce to help us further develop the plant and the economic wellbeing of its employees, local communities and Romania.”

Liberty Steel Continental Europe chief executive Jon Bolton adds: “Galati is a strategically located operation, with an excellent and highly skilled workforce in one of the fastest-growing economies in Europe.”

Liberty said last November it would likely relaunch one of Galati’s two idle blast furnaces. It would also consider the restart of the other idle BF or installation of an electric arc furnace that would use scrap as feedstock (see Kallanish passim). It said in addition that it will study starting production of auto sheet to supply Romania-based carmakers.

Liberty Steel commits 220 M€ in Galati plant .