The modernization enables the company to achieve a significant increase in efficiency, also improving the energy efficiency of the plant and reducing maintenance costs. The average shift output has been increased by five percent.
The modernization works lasted 35 days and were carried out during the 2019-20 winter shutdown in order to minimize disruption of production.